Cutover
Cutover is a process used to transition an organization from one system to another. The UNF cutover operation involves transferring data and processes from Banner to Workday. This page will show timeline details, scenarios, and deadlines for different activities.
Workday Cutover Timeline
High-level Dates
Note: Many transactions have deadlines prior to these dates. Please see the detailed cutover table below for specifics.
- May 3, 2024 – Hard freeze on requisitions, iContracts and change orders
- May 31, 2024 - Hard freeze on travel requests and travel bypasses in Concur
- June 7, 2024 – Hard freeze on job postings
- June 14, 2024 – Last recommended day to use P-Cards to ensure expenses hit FY24
- July 1, 2024 – Workday is available for use University wide
Work Area | Activity | Hard Freeze Date | First day for Transaction in Workday | Notes and Communications |
---|---|---|---|---|
Procurement | Deadline for furniture request | March 15, 2024 | July 1, 2024 | |
Human Resources |
Deadline to close postings that are not active in OASys | April 30, 2024 | N/A |
|
Procurement | Last day for FY24 Requisitions, iContracts, and Change Orders | May 3, 2024 | July 1, 2024 | |
Human Resources | Summer A – Contract Start Date | May 6, 2024 | July 1, 2024 |
|
Human Resources | Summer A – ePAF deadline | April 22, 2024 | July 1, 2024 |
|
Procurement | Deadline for iContracts | May 3, 2024 | July 1, 2024 | |
Procurement | Deadline for Supplier Registration | May 3, 2024 | July 1, 2024 | |
Human Resources | Summer B – Contract Start Date | June 24, 2024 | July 1, 2024 | Summer B – will be paid out of Workday |
Human Resources | Summer B – ePAF deadline | May 8, 2024 | July 1, 2024 |
|
Human Resources | Summer C - Contract Start Date | May 6, 2024 | July 1, 2024 |
|
Human Resources | Summer C - ePAF deadline | April 22, 2024 | July 1, 2024 | Submit ePAFs after contracts are approved and sent to HR |
Human Resources |
Final Day for fully approved ePAFs/PAFs to be sent to Human Resources for SPIs, Reclassifications and Promotions to be effective May 25, 2024
|
May 20, 2024 | July 1, 2024 | Reminder that these must be approved in OASYS/Banner Online Forms prior to the ePAF/PAF being submitted. |
Travel | Last day to submit Travel Requests and Travel Bypasses in Concur | May 31, 2024 | July 1, 2024 | Concur Travel Closeout Procedures |
Procurement | Last day for Procurement to issue FY24 POs | May 31, 2024 | July 1, 2024 | |
Budget | Last day to submit Auxiliary Budget Oversight (ABO) requests for FY24 | May 31, 2024 | July 1, 2024 | |
Budget | FY25 Self Service Budget Development (SSBD) budgets posted in Banner. | June 3, 2024 | Budgets will be available to view in Workday July 1, 2024 | |
Human Resources |
Final day to submit an ePAF/Hiring Proposal if unable to hire students/OPS by May 10, 2024 | May 27, 2024 | July 1, 2024 | This includes rate changes for OPS/Students as well |
Human Resources |
Hard freeze on all hiring for students and OPS | May 28, 2024 | July 1, 2024 | This includes both rehires as ePAFs and new hires in OASYS |
Human Resources | Last day to post job requisitions in OASYS | June 7, 2024 | July 1, 2024 | |
Payroll | Last payroll completed in Banner (Pay period 13) | June 8, 2024 - June 24, 2024 | N/A | Pay Date June 28, 2024 |
Human Resources | Hard freeze on all employee job changes | May 28, 2024 - July 1, 2024 | July 8, 2024 | This includes:
|
Human Resources | Last new employee orientation before Workday | May 28, 2024 | July 8, 2024 |
|
Human Resources |
Hard freeze on New Hires | June 10, 2024 | July 8, 2024 |
|
Procurement | Last day to use P-Cards to ensure transactions will post to FY24 | June 14, 2024 | July 1, 2024 | |
Travel | Last day to use P-Card to ensure expenses hit FY24. |
June 14, 2024 | July 1, 2024 | |
Accounts Payable | Last day to submit and approve all Concur reports for FY24 | June 21, 2024 | July 1, 2024 | |
Travel | P-card and Travel Expenses reports must be fully approved by departments. (Including Vicinity/Blanket expense reports) |
June 21, 2024 | July 1, 2024 | |
Accounts Payable | Last day to submit direct pay requests, invoices against encumbrances and icontracts. | June 21, 2024 | July 1, 2024 | |
Foundation | Final day to submit $5,000 and over check requisitions to UNF Foundation | June 24, 2024 | July 1, 2024 | Foundation has the same deadlines for requisitions, p-card use and expense reports as the University. |
Foundation | Final day to submit normal check requisitions (less than $5,000) to UNF Foundation |
June 25, 2024 | July 1, 2024 | Foundation has the same deadlines for requisitions, p-card use and expense reports as the University. |
Student Financial Services | Final day to deposit refunds for FY24 expenditure reimbursements (includes Foundation Reimbursements)
|
June 28, 2024 | July 1, 2024 | Any deposits submitted after the deadline will post in the next fiscal year |
Accounts Payable | Final FY24 check run | June 28, 2024 | July 3, 2024 | |
Human Resources |
First day to post jobs in Workday | N/A | July 1, 2024 | |
Payroll | First payroll completed in Workday (Pay period 14)
|
N/A | June 22, 2024 - July 5, 2024 |
|
Procurement | First day for FY25 Requisitions and POs in Workday | N/A | July 1, 2024 |
Workday Go Live ~ July 1, 2024
-
What is "Cutover"?
Cutover is a process that is used to transition an organization from one system to another. This project will involve the transfer of data and processes from our old systems to Workday.
-
What are "Freeze Dates"?
Freeze dates are required dates that support cutover activities. They can also be considered "cutoff dates". Each legacy system will have a “soft freeze” date. During this time, we slow down the transactions entered into legacy systems as much as possible. Each legacy system will also have a "hard freeze" date; after which no more transactions may be enter into the legacy system; all future transactions will be entered directly into Workday.
-
What are the Workday testing stages?
There are four types of testing stages that will occur. The testing stages are: Unit testing, End-to-to-End (E2E), Payroll Parallel and Production Dress Rehearsal (PDR). To learn more about each testing stage, visit our Testing Stage webpage. -
What happens after testing?
The Workday system will be prepared for training and launch following testing.
More to come.