Project Milestones Date
Project Started October, 2002
Project Definition Approved February, 2003
Hardware Installed January, 2003
Software Installations  
Banner Software Installed January, 2003
Web for Products Installed January, 2003
Banner Finance  
Business Interviews Completed February, 2003
Project Schedule Completed December, 2002
Training Started March, 2003
Finance Go-Live* July, 2004
Banner Human Resources  
Business Interviews Completed August 2003
Project Schedule Completed April, 2003
Training Started August, 2003
HR Go-Live* January, 2005
Banner Student  
Business Interviews Completed November, 2003
Project Schedule Completed July, 2003
Training Started December, 2003
ST Go-Live* April, 2005
Banner Financial Aid  
Business Interviews Completed December, 2003
Project Schedule Completed August, 2003
Training Started February, 2004
FA Go-Live* January, 2005
PIA's Completed December, 2005
Project Closeout Completed December, 2005