CMS Project Plan

System Installation & Pre-Launch

To see the detailed migration status of each division and department, visit the migration status page

Project plan
% Complete Task Name Duration in days
100% Current Site Analysis 20 days
100% Executive Summary Justifying CMS Acquisition 3 days
100% Request for Information sent to Vendor List 5 days
100% Request for Proposal Process 10 days
100% WAC Recommends Ektron CMS & 352 Media Group 3 days
100% CMS Coordinating Committee Formed 5 days
100% Ektron CMS-400 Purchased 5 days
  Project Kick-Off  
100%       Strategic Initiatives & Integration 20 days
100%       Research - Top Ektron sites 90 days
  Ektron Training  
100%       Ektron Developer Admin Training 5 days
100%       Ektron Ed User Training 6 days
  CMS System Preparation  
100%       352 modifications 90 days
100%       System Version upgrades 5 days
100%       Server Synchronization 20 days
  ISA Collaboration  
100%       Coordinate with Systems Engineering 20 days
100%       Design and Implement Security Model 20 days
  Determine Info Architecture  
100%       Analyze current site structure, size and ownership 20 days
100%       Develop CMS folder structure 3 days
  Template Design  
100%       Research other university sites 5 days
100%       Redesign UNF homepage & subpage templates 30 days
100%       Develop template code 20 days
100%       Research dynamic page building 20 days
  Support Plan  
100%       Support web site 10 days
100%       Knowledge Base - Help Desk 25 days
100%       Develop & document support model & roles 10 days
  UNF CMS Training  
100%       Develop Training plan 15 days
100%       Develop manuals 25 days
100%       Set up Training Environment 10 days
  MIgration Plan  
100%       Create migration detail document 2 days
100%       Create migration status web page 2 days
  Migration of Top Level Pages  
100%       Migrate content 5 days
100%       IPC Reviews & changes 15 days
100%       Testing & approval 10 days
100%       System Version Upgrades 5 days
100%       Server Synchronization - Test & Production 20 days
  Catalog  
100%       Migration of catalog text & images 30 days
100%       Integration with Banner 20 days
100%       Training 4 days
100%       End-user editing & support 15 days
100%       Review 7 days
  Development & Integration  
100%       Dynamic List Summary 7 days
100%       Photo Gallery 21 days
100%       Flash & Multimedia 15 days
100%       Keywords 10 days
100%       Page Metadata (SEO) 3 days
100%       Campus Map 60 days
  Go Live with main pages