Re-affirmation Timeline
Major SACS Preparatory Tasks and Associated Timeline |
|||
| Fall 2009 | Re-accreditation Decision by SACS Commission on Colleges | December | |
| Summer 2009 | Preparation & Submission of Response to Onsite Peer Review Team Report |
Jul - Aug | |
| Spring 2009 | Receipt of Report of Onsite Peer Review Team | Feb - Mar | |
| Onsite Peer Review | Feb 10-12 | ||
| Submission of Quality Enhancement Plan | Dec 19 | ||
| Submission of Focused Report | Dec 19 | ||
| Fall 2008 | Preparation of Focused Report Responding To Compliance Certification Review | Nov - Dec | |
| Offsite Peer Review of Compliance Certification | Nov 3-6 | ||
| Fall 2008 | Submission of Compliance Certification | Sept 10 | |